Mpumalanga, Limpopo and North West Schedules
Project Start Date: 2/3/2020 (Monday)
WBS | Task | Start | End | Venue | Duration |
---|---|---|---|---|---|
1 | March | ||||
1.1 | Optic Fibre Splicing & Testing | Mon 3/23/20 | Fri 4/03/20 | Nelspruit | 10 |
2 | May | ||||
2.1 | Optic Fibre Splicing & Testing | Mon 5/04/20 | Fri 5/15/20 | Polokwane | 10 |
3 | June | ||||
3.1 | Optic Fibre Splicing & Testing | Mon 6/29/20 | Fri 7/10/20 | Mahikeng | 10 |